New PPP Waste Management Project for A Waste Processing Unit in Ano Liossia, Western Attica
The project concerns the financing construction, maintenance and operation of a waste processing unit for Western Attica.
The facility will process approximately 400,000 tones of waste per year for a duration of 27 years. The exact amount of waste to be processed along with the possibility of extending the duration of the engagement will be discussed during the competitive dialogue as will the possibility of the inclusion of a composting unit for per sorted waste.
EDSNA will participate by covering 40-60% of the construction cost ( estimated cost based on 50% financing is 205- 255 million Euros).
Offers must be submitted by 12:00pm on 29/1/2013.